Strokes per Minute Required for Target Annular Velocity Formula

SPM=AVACqoSPM=\frac{AV\,AC}{q_o}

Strokes per Minute Required for Target Annular Velocity calculates pump speed required for drilling hydraulics workflows in drilling engineering.

Calculate

How engineers use this formula

Use this formula when the listed inputs (AV, AC, q_o) are known and the assumptions behind the cited drilling hydraulics relationship match the engineering case being checked.

Assumptions

  • Input values are representative for the well, reservoir, fluid, or equipment case being evaluated.
  • The declared units match the field-unit constants used in the formula.
  • The cited formula applies to the selected petroleum engineering workflow.

Limitations

  • The calculation does not replace a full engineering model or operating procedure.
  • Accuracy depends on the source correlation, assumptions, input quality, and unit consistency.

Common mistakes

  • Mixing unit systems without converting the inputs.
  • Using default example values as field recommendations.
  • Applying the formula outside the source assumptions.

Default example

Using the default inputs, SPM equals 75 strokes/min.

AVft/min

150

ACbbl/ft

0.05

q_obbl/stroke

0.1

Inputs

AV

ft/min

Target Annular Velocity

AC

bbl/ft

Annular Capacity

q_o

bbl/stroke

Pump Output

Outputs

SPM

strokes/min

Pump Speed Required

AV

ft/min

Target Annular Velocity

AC

bbl/ft

Annular Capacity

q_o

bbl/stroke

Pump Output

Source and review

reviewed

Lapeyrouse, N.J. Formulas and Calculations for Drilling, Production and Workover, 2nd Edition, Page 12.

Source

Related formulas and calculators

Hydrostatic Pressure from Mud Weight
Well Control
Surface Pressure During Drill Stem Test
Well Control
Specific Gravity to Fluid Weight
Well Control
Kick Analysis - Influx Density
Well Control
Kick Analysis - Formation Pressure With Well Shut-In
Well Control
Kick Analysis - Shut-In Drill Pipe Pressure
Well Control